TRU Stakeholder Update - July 2026
|
|
|
Good afternoon,
Welcome to the July edition of our Transpennine Route Upgrade (TRU) monthly stakeholder update. Each month, we share key milestones, news, and upcoming activity as we continue transforming the railway across the North of England.
As a multi-billion-pound programme, TRU is more than a railway upgrade - it's a catalyst for economic growth, regeneration and sustainable development. By improving connectivity between key towns and cities, we are helping to unlock new opportunities for communities and businesses across the region.
Through faster, more reliable, and greener services for passengers and freight, TRU is driving the Northern economy forward – improving productivity, supporting jobs and skills, and laying the foundation for long-term prosperity. July's key updates at a glance:
- Dewsbury & Batley: Key progress delivered
- Bridge removals pave the way for electrification
- Community Fund projects begin transforming local commnuities
- A lookahead to major works on TRU
|
|
|
|
TRU social value impact
We believe sustainable development is the only way to keep us on track to a better future for rail in the North. Our commitment to people and place continues to deliver results. We are supporting Northern talent, boosting local economies, and creating a more sustainable future. Our latest totals this period: |
|
|
£947.3m spent with local businesses
|
|
£481m spent with SME businesses |
|
|
|
|
Curious about the impact in your area?
We would be happy to share the social value figures for your local community – from jobs and apprenticeships to local business spend and volunteering hours. Just get in touch, and we will bring the story closer to home. |
|
|
| Help us improve – take our survey |
|
|
We want to keep improving how we communicate with you. Please take five minutes to complete our short survey and share your feedback
|
| Fill in the survey here
|
|
|
| Dewsbury & Batley: Key progress delivered |
 |
TRU teams have successfully completed 28 days of intense engineering works between Morley and Dewsbury, delivering another important step towards a faster, more reliable, and greener railway. During 30 May to 27 June, we completed a wide range of improvements that will support future services and improve the customer experience, including:
- Renewing track and drainage to improve railway reliability
- Installing foundations and masts to support future electrification
- Upgrading Batley station, with longer platforms and improved customer facilities
- Enhancing Dewsbury station with extended platforms, improved roof canopies and a strengthened footbridge
- Reconstructing Jack Lane bridge in Dewsbury to create the clearance needed for future electrification longer trains
While significant progress has now been made, work will continue in the coming months, including further improvements at Huddersfield station throughout the summer. |
|
|
|
Bridge removals mark progress towards electrification |
Two bridges between Cross Gates and Micklefield have now been removed as part of preparations to electrify the route. The existing Austhorpe Lane bridge and Ridge Road bridges did not provide enough clearance for the overhead line equipment needed to power cleaner, quieter electric trains. Their removal marks another important milestone in modernising the railway.
As part of our commitment to reducing waste, stone from the original structures is being refurbished and will be reused to clad the replacement bridges when they are installed later this summer, helping to retain the character of the local area. |
 |
| Community projects already making a difference |
|
|
Communities along the route are already seeing the benefits of the 2025 TRU Community Fund. The fund provided grants up to £20,000 to support projects within five miles of the TRU route, helping local organisations improve community spaces, create new opportunities and strengthen neighbourhoods.
Projects completed so far include: - Rise in Unity youth hub, Huddersfield – a new kitchen and dining space, providing a safer and more welcoming environment for young people
- Monk Fryston School, Leeds – a new cycle shelter encouraging active and healthier journeys to school
- The Barn, Tadcaster – upgraded kitchen facilities supporting a thriving community hub
Many more projects are underway creating greener spaces, improving accessibility and supporting skills and learning opportunities, wellbeing and community connections. Applications for the next round of TRU Community Fund will open later this year. We will keep you updated as further details and application dates are announced. |
 |
|
|
| A lookahead to major works on TRU |  |
Two major phases of engineering work are planned this autumn as TRU continues to improve the railway between Manchester, Huddersfield, Leeds, and York. Marsden to Mirfield improvement works (19 September - 4 October)
- Key works: The programme will include track and drainage renewals, station improvements at Huddersfield and Deighton, and further installation of overhead line equipment to support future electrification.
Train service changes: Huddersfield and Slaithwaite stations closed, with an amended timetable operating between Stalybridge and Mirfield. Services will be diverted where possible, with rail replacement buses also in operation. Additional stations will be closed on the weekends of 19 & 20 September and 3 & 4 October.
Church Fenton bridge replacement (24 October - 1 November) - Key works: We will demolish and replace the Common Lane bridge in Church Fenton creating the clearance needed for future electrification.
Train service changes: - 10–11 October (advance works): No trains will run between York and Leeds, with rail replacement buses in operation to keep customers moving.
- 17–18 October (advance works): Train services diverted via Castleford.
- 24 October – 1 November: No trains will run between York and Leeds for nine days, with rail replacement buses in operation to keep customers moving.
Further details will be shared in due course. Customers are encouraged to check journeys in advance at at nationalrail.co.uk. |
|
|
| Upcoming engineering work: what to expect | Work continues throughout the summer as we deliver improvements across the route. For more details, please contact us.
Manchester to Huddersfield/Leeds - Saturdays & Sundays, 4 & 5, 11 & 12, 18 & 19, 25 & 26 July and 1 & 2 August We will continue transforming Huddersfield Station, including installing sections of the new station roof, extending platforms, completing the new footbridge and commissioning new lifts.
There will be no trains between Stalybridge and Mirfield, and no trains at Huddersfield Station. Services between Manchester and Leeds will be diverted via the Calder Valley route, with rail replacement buses serving stations that cannot be accessed by train. Bradford Forster Square to Leeds - Sunday 19 July, Sunday 26 July and Saturday 1 to Monday 3 August
Construction continues at the Shipley Train Care Centre, with new Under Track Crossings and drainage improvements to support the future operation of the facility. Customers will be kept on trains wherever possible, however for services where this is not possible, rail replacement buses will be in place.
Leeds to York/Selby – Saturdays & Sundays, 8 & 9, 15 & 16 and 22 & 23 August We will install replacement bridges at Austhorpe Lane and Ridge road, renew sections of track and continue preparing the route for electrification.
Long distance services will be diverted, while services to and from local stations will be replaced by buses. Manchester to Huddersfield/Leeds - Saturdays & Sundays, 5 & 6 and 12 & 13 September
Work will continue at Ravensthorpe, Mirfield, Deighton and Huddersfield as we install new track, progress station improvements and prepare for future overhead line equipment. There will be some changes to services, with customers kept on trains wherever possible, however for services where this is not possible, rail replacement buses will be in place. |
|
|
|
|
|
To deliver upgrades safely, a number of road closures are in place or planned. If you would like more information about the works, please contact us.
Deighton Whitacre Street: Closed until December 2026. Colliery Bridge / Wheatleys: Closed until early 2027
Birkby Bradley Greenway: Closed until summer 2026. A62 Leeds Road: Closed to vehicles on four weekends between 10 July - 3 August 2026. Access open to pedestrians throughout.
Colne Bridge Road: Closed to vehicles until Friday 17 July 2026 (excluding 11-12 July). Also closed 7-8 August. Access open to pedestrians throughout. Huddersfield
John William Street: Closed 3-6 July, 10-13 July, & 31 July - 3 August 2026. Fitzwilliam Street: Closed until Friday 7 August 2026. A641 Bradford Road / Northgate: Closed from Monday to Fridays, between 3-28 August 2026.
Cross Church Street: 21-23 August 2026 Please note that the A641 Bradford Road / Northgate, A62 Leeds Road and Colne Bridge Road will not be closed at the same time during this period.
The full list of the Huddersfield road closure dates can be found on our website.
Ravensthorpe Calder Road: Closed to vehicles until autumn 2026. Calder Valley Greenway: Closed until September 2027.
Spen Valley Greenway: Closed until September 2027. Batley Jack Lane: Closed to vehicles until Friday 31 July 2026. Closed to pedestrians from Wednesday 10 June until Friday 31 July 2026.
Dewsbury George Street: Closed from Monday 27 July for 4 weeks. Garforth & Micklefield
A656 Ridge Road: Closed over the railway line from Monday 2 March until Friday 4 December to enable the bridge to be reconstructed to accommodate the overhead line equipment needed to power greener, quieter, faster electric trains.. Traffic will be diverted via the A63 and A642 along a clearly signposted diversionary route. Cross Gates
Austhorpe Lane: Closed over the railway line between 7 April 2026 and 15 January 2027 to enable the bridge to be reconstructed to accommodate the overhead line equipment needed. Traffic will be diverted via Austhorpe Road, Station Road and Ring Road Halton. Church Fenton
Common Lane: Closed over the railway line from Monday 13 July 2026 until Friday 4 June 2027 to enable the bridge to be reconstructed to accommodate the overhead line equipment needed to power greener, quieter, faster electric trains. Traffic will be diverted via Sherburn-in-Elmet along a clearly signposted diversionary route. Whilst a temporary extension to the existing station footbridge will enable pedestrians and cycles to cross the line.
| |
|
|
|
|
|
|
|
We want to thank you for your continued support as TRU transforms the railway in the North of England. If you have questions or want to speak with us, please email: TRUCommunications@networkrail.co.uk.
For more information about the programme, please visit theTRUpgrade.co.uk.
Warm regards, Team TRU |
|
|
|